Building sector failing on supervision
Senior ICE Scotland members discuss the 2017 inquiry into Scottish building failures which showed the need for more supervision on all sites.
Contents |
[edit] Introduction
In January 2016, storm Gertrude caused a substantial section of the upper level of an external brickwork facade of Oxgangs School in Edinburgh to collapse onto a pathway below. Fortunately it was early in the morning and the school was deserted.
The school and 15 others were built under a public–private partnership (PPP) project for the City of Edinburgh Council and were completed by 2005. Following inspection similar problems were evident over all school buildings in the PPP scheme so all were closed and repaired during 2016.
The council commissioned an inquiry led by John Cole (2017). This found a catalogue of construction failures including inadequate tie embedment, varying cavity width, poor wall verticality, missing or inadequate head restraint and missing bed reinforcement issues. Construction had been carried out under a quality assurance regime but there was almost no traditional site inspection undertaken. Lack of as-built records were a further issue.
[edit] Lack of supervision
The Scottish government sought industry comment on the inquiry report and ICE Scotland’s response was taken forward by its public voice committee. Subsequently written evidence was also given to the education and skills committee of the Scottish parliament.
ICE Scotland found little to disagree with in the inquiry report. It noted that on building projects there are typically multi-disciplinary involvements which can lead to challenges when considering technical supervision, which is sometimes on a visiting basis. In civil engineering this is usually carried out on a full-time basis – and arguably is necessary for managing the contractual process.
Experience suggests that supervision, inspection and testing has diminished over the years for financial reasons. Building is a production industry but while other production industries have focused on quality control the building industry typically produces complex and mostly unique products. Basic quality checking has been engineered out in many cases.
[edit] Risk analysis approach
ICE Scotland considered that in all likelihood the problems identified in Scotland exist elsewhere irrespective of the procurement method. Clients therefore need to adopt appropriate supervision methodologies based on a risk analysis approach – certainly they should not delegate supervision to their contractors.
PPP, design-build-finance-operate, and design-build contract forms can be adapted to ensure that mandatory supervision is provided in a transparent way. Construction records are an essential part of project completion and should be required prior to facility use.
In July 2017, the Scottish government issued interim guidance for site inspection and assurance for public sector clients. Construction Scotland was tasked to advise the government on steps being taken and ICE Scotland is playing its part.
Issues being developed include training and verification of brickwork apprentices, technical guidance detailing for masonry, best practice in quality assurance systems, continual professional development training in brickwork detailing and design coordination best practice.
[edit] Back to basics
It is perhaps hard to believe that these failures occurred in the early-21st century. Project management, programme management and quality assurance systems all have their place but perhaps the construction industry needs to relearn the basics.
A project needs to be properly designed and the design needs to be appropriately checked. The design needs to be translated into construction and the construction needs to be independently supervised. Design alterations need to be referred to the designer and adequate as-built records need to be produced.
It all sounds very basic – and it is.
This article was originally published here by ICE on 5 June 2018. It was written by Ronnie Hunter, ICE council member for Scotland, and Jim Young, ICE Scotland senior vice chair.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.